PM Surya Ghar last date: your checklist before 31 March 2027
The PM Surya Ghar Muft Bijli Yojana is scheduled to close on 31 March 2027. There is no official notice yet about what happens to applications that are still unfinished on that date. This guide gives you a step-by-step plan for your situation, so your ₹78,000 subsidy does not get stuck.
Watched our video? This is the full checklist we promised. Haven’t seen it yet? Watch the video on YouTube.
What we know, and what is only reported
Everything in this guide is marked the same way as in our video. Green boxes are facts with a source. Gold boxes are our own reading or prediction, which can turn out wrong.
- The scheme was launched in February 2024 with a ₹75,021 crore outlay and a target of one crore homes. Central subsidy is ₹30,000 for 1 kW, ₹60,000 for 2 kW and ₹78,000 for 3 kW or more.
- The Centre is considering a three-to-four-month extension beyond March 2027, and consultations on a successor scheme are underway. Neither has been notified (EQ, 5 Sep 2026).
- When the old rooftop scheme was replaced in 2024, applications submitted before 13 February 2024 stayed on the older, lower subsidy (Energetica India). The application date decided the scheme, not the installation date.
- The subsidy is released only after installation, net metering and DISCOM inspection are complete.
The one rule history has confirmed is that your application date decides which scheme you fall under. Every plan below is built so that it works whether the extension comes or not.
Pick your situation
Jump straight to the plan that fits you. Each one is the same as the matching chapter in the video.
- AI haven’t applied yet
- BMy sanctioned load is under 3 kW
- CMy application is stuck
- DI need a battery for power cuts
- EI rent, or I live in a flat
The six stages every application goes through
Every plan below refers to these stages. Your ₹78,000 only moves at the last one, so a delay at any earlier stage delays the money.
- Register and applyYou
- Technical feasibilityDISCOM
- InstallationVendor
- Plant details and net meter requestVendor
- Net meter, inspection, commissioning certificateDISCOM
- Subsidy claim and payoutYou
According to the portal process, the DISCOM handles feasibility approval, the net meter and the inspection. Once the commissioning certificate is generated, you submit your bank details and a cancelled cheque, and the subsidy is due within 30 working days (Vikaspedia). The official helpline is 15555.
I haven’t applied yet
You own your house, you have a usable roof, and you have not registered on the portal. This is the largest group, and you have the most to gain from starting this month.
- Pull out your latest electricity bill Note three things: your consumer number, your sanctioned load in kW, and the exact name on the bill. The portal will not allow a system larger than your sanctioned load. If your load is under 3 kW, follow plan B first.
- Match your bank account to the bill The name on your bank account must match the name on the electricity bill, spelling included, and the account should be linked to your Aadhaar. A single mismatched letter is one of the most common reasons a subsidy gets held up. Fix it with your bank now, not after installation.
- Decide your system size The subsidy stops growing at 3 kW, so every kW above 3 is paid entirely by you. Size the system to your actual consumption: check your last 12 bills and look at the average monthly units, especially in summer.
- Register and apply on the national portal Go to pmsuryaghar.gov.in, select your state and DISCOM, and register with your consumer number and mobile number. Then submit the rooftop solar application. Your application date is set at this step.
- Choose a vendor registered with your DISCOM, and ask before you sign
- Do you have DCR (Made in India cell) panels in stock today? The subsidy requires them, and their prices rose 20 to 23 percent this year when demand spiked (Indian Express via Vision IAS).
- How long does net metering take in my DISCOM right now?
- Will you write a completion date into the agreement?
- What does the structure stand on, and who fixes it if the roof leaks?
- Wait for feasibility approval before installation starts The DISCOM checks whether your connection can take the system. Do not let anyone install before this approval arrives, or the system may not qualify.
- Install, then request the net meter After installation, the vendor uploads the plant details and applies for the net meter. Follow up with the vendor until the request shows on your portal dashboard.
- Claim the subsidy the day the commissioning certificate appears Upload your bank details and a cancelled cheque immediately. Delhi residents can also claim the state capital subsidy and generation-based incentive through their DISCOM, which pays it against the first bill after the net meter is installed (Delhi EE&REM Centre).
Your working calendar
Work backwards from the deadline and keep March empty as a safety margin.
My sanctioned load is under 3 kW
This is very common in Delhi. Your bill says 1 or 2 kW, but you want a 3 kW system for the full ₹78,000. The portal caps your system at the sanctioned load (Heaven Green Energy), so the load must be fixed first.
- Confirm the gap Compare the sanctioned load on your bill with the system size you want. A 2 kW load allows a 2 kW system and ₹60,000. Raising it to 3 kW unlocks ₹78,000.
- Apply for load enhancement now Apply on your DISCOM’s website or at its customer care office. This is usually the slowest step in the whole process, so start it before anything else. Keep the receipt and the request number.
- Wait for the new load to show on your bill or account Apply for solar only once the enhanced load is reflected. A mismatch between the load on record and the system you apply for is a common reason feasibility gets rejected.
- Use the 10 percent panel allowance MNRE has advised DISCOMs to allow up to 10 percent more panel (DC) capacity than the sanctioned load, as long as the inverter (AC) stays within the load (Energetica India). Confirm that your DISCOM follows the advisory before you size the system.
- Then follow plan A from step 4 Register and apply, choose your vendor, and keep to the working calendar.
| Sanctioned load | Inverter (AC) limit | Panel (DC) limit with 10% | 540 W panels that fit |
|---|---|---|---|
| 2 kW | 2 kW | 2.2 kWp | 4 panels (2.16 kWp) |
| 3 kW | 3 kW | 3.3 kWp | 6 panels (3.24 kWp) |
| 5 kW | 5 kW | 5.5 kWp | 10 panels (5.40 kWp) |
My application is stuck
You applied, but the status has not moved for weeks. The fix depends on which stage you are stuck at and who owns that stage.
- Find your exact stage Log in to pmsuryaghar.gov.in and note the status shown on your dashboard. Take a screenshot with the date.
- Find the owner of that stage in the table below Chasing the wrong party wastes weeks. A vendor cannot speed up a DISCOM inspection, and a DISCOM cannot fix your bank details.
- Follow up in writing Email or message the owner with your application number and the screenshot. Written follow-ups create a record you can escalate with.
- Escalate if nothing moves Call the national helpline 15555, raise a complaint with your DISCOM’s solar cell, and keep the complaint numbers.
| Where it’s stuck | Owner | Common cause | What to do |
|---|---|---|---|
| Registration | You | Wrong consumer number | Re-register with the exact details from your bill |
| Feasibility pending | DISCOM | Backlog, or load mismatch | Check your sanctioned load (plan B), then follow up with the DISCOM’s solar cell |
| Installation | Vendor | Panel shortage, overbooked crews | Ask for the written completion date and proof of panel stock |
| Net meter or inspection | DISCOM | Inspection queue | Follow up in writing; escalate via 15555 and the DISCOM |
| Subsidy not credited | You and your bank | Name mismatch, Aadhaar not linked to the account | Fix bank KYC, then resubmit the claim on the portal |
If your solar loan is stuck
Loan rejections are a large hidden bottleneck. Public sector banks rejected 305,667 of 803,515 PM Surya Ghar loan applications (Outlook Business). Reported reasons include missed electricity bill payments and land records still in the name of deceased relatives (Reuters via BusinessDay).
- Clear any pending electricity dues before you apply.
- Update property records into the current owner’s name if needed.
- Ask for the rejection reason in writing, and apply with another participating bank if the reason is fixable.
I need a battery for power cuts
Your area has frequent or long outages, and an on-grid system alone switches off when the grid goes down. You may be tempted to wait for a battery subsidy.
Batteries are allowed under the current scheme but are not separately subsidised; the central payout stays capped at 3 kW of solar whether or not you add a battery (UTL). Battery support in PM Surya Ghar 2.0 is under discussion but has not been notified (Arka360).
- Install solar now and secure the ₹78,000 Follow plan A. The solar subsidy is available today; the battery subsidy is not.
- Make the system battery-ready Ask your vendor for a design that can take a battery later, either a hybrid inverter or a layout that allows a battery to be added on the AC side. Leave wall space and a cable route near your main distribution board.
- Decide whether the battery is a comfort purchase or a wait If outages are severe and daily, buying the battery now is a comfort decision; budget it separately from the subsidy maths. If outages are occasional, add the battery once any 2.0 support is officially notified.
- Reject any quote that counts a 2.0 battery subsidy No amount or eligibility rule has been announced. A quote that subtracts one is promising money that does not exist yet.
I rent, or I live in a flat
The individual subsidy needs a household that owns its house and has a suitable roof (Drishti IAS). That rules out most renters and flat owners on their own, but there are still two routes.
If you live in a flat: take it to your RWA
Group housing societies and resident welfare associations can claim ₹18,000 per kW for common facilities, including EV charging, on systems up to 500 kW (Vikram Solar). Solar on the society roof cuts the common-area bill for lifts, water pumps and lighting, which lowers everyone’s maintenance charges.
- Collect 12 months of common-area electricity bills These show how much the society spends and how large a system makes sense.
- Measure the usable, shadow-free roof area Exclude water tanks, lift rooms and areas shaded by taller buildings.
- Get a resolution passed at the RWA meeting The society applies as one body, so it needs a formal decision and an authorised signatory.
- Apply on the portal as a GHS or RWA before the deadline The same 31 March 2027 end date applies, and society approvals take longer than individual ones, so start early.
If you rent: the owner applies
The electricity connection and the subsidy belong to whoever holds the connection, which is usually the owner. If you plan to stay for years, discuss sharing the cost and the savings with your landlord before the deadline.
Proposals for PM Surya Ghar 2.0 include shared solar and virtual net metering for apartments and multi-tenant buildings (Ornate Solar). This is the one group for whom waiting for the next scheme is the sensible choice.
Our four predictions, on record
In the video, Shashwat made four dated predictions. We will score each one publicly in April 2027, right or wrong.
- The extension will cover finishing, not starting. It will protect applications already in the pipeline, not new ones filed late.
- PM Surya Ghar 2.0 will pay urban homes less upfront. Reported proposals vary support by household income and location (Energetica India).
- February 2027 will be the worst month to install. Panels, installers and DISCOM inspections will all have the longest queues.
- Battery support will come, but not before July 2027.
If all four are wrong, the plans above still hold, because each one finishes well before the deadline and keeps the battery option open.
Frequently asked questions
What is the last date for PM Surya Ghar?
The scheme is scheduled to end on 31 March 2027. A three-to-four-month extension is being considered but has not been officially notified as of 10 October 2026.
Will I get the subsidy if my installation is not finished by 31 March 2027?
There is no official notice on unfinished applications yet. The subsidy is released only after installation, net metering and DISCOM inspection, so the safe plan is to have your commissioning certificate by mid-February 2027.
Has PM Surya Ghar 2.0 been announced?
No. PM Surya Ghar 2.0 is a set of reported proposals, including generation-linked support, battery storage and shared solar for apartments. Do not accept any quote that counts a 2.0 subsidy.
Can I get the subsidy if my sanctioned load is 2 kW?
Yes, for a system up to your sanctioned load: a 2 kW system gets ₹60,000. To get ₹78,000 you need a load of at least 3 kW, so apply for load enhancement first.
How long does the subsidy take after commissioning?
After the commissioning certificate is generated and you submit correct bank details with a cancelled cheque, the subsidy is due within 30 working days.
Can flat owners get the PM Surya Ghar subsidy?
Not individually without their own roof. A housing society or RWA can claim ₹18,000 per kW for common facilities on systems up to 500 kW.
Is there a subsidy for solar batteries?
Not under the current scheme. Batteries are allowed but not separately subsidised. Battery support is under discussion for PM Surya Ghar 2.0.
Want us to check your bill before you apply?
Send us a photo of your latest electricity bill. We’ll tell you your sanctioned load, the system size that fits, and whether you can finish before the deadline.
Lumencity has installed solar since 2014: 275+ MW across 7,000+ sites, rated 4.9 on Google.
Sources
- EQ: PM Surya Ghar scheme could get extension (5 Sep 2026)
- Energetica India: applications before 13 Feb 2024 ineligible for new CFA
- Vikaspedia: National Portal for Rooftop Solar, application steps
- Delhi EE&REM Centre: installation process for consumers
- Energetica India: MNRE 10% DC capacity tolerance
- Energetica India: PM Surya Ghar 2.0 proposals
- Outlook Business: PSB rooftop solar loan rejections
- Vikram Solar: subsidy guide, including GHS/RWA rates